Incentive scheme for efficient grid utilization in the Swedish revenue cap regulation from 2020

dc.contributor.affiliationThe Swedish Energy Markets Inspectorate
dc.contributor.affiliationThe Swedish Energy Markets Inspectorate
dc.contributor.affiliationThe Swedish Energy Markets Inspectorate
dc.contributor.affiliationThe Swedish Energy Markets Inspectorate
dc.contributor.affiliationThe Swedish Energy Markets Inspectorate
dc.contributor.authorWallnerström, Carl Johan
dc.contributor.authorWigenborg, Gustav
dc.contributor.authorHuang, Yalin
dc.contributor.authorStröm, Lars
dc.contributor.authorJohansson, Tommy
dc.contributor.countrySweden
dc.contributor.countrySweden
dc.contributor.countrySweden
dc.contributor.countrySweden
dc.contributor.countrySweden
dc.contributor.detailedauthorWallnerström, Carl Johan, The Swedish Energy Markets Inspectorate , Sweden
dc.contributor.detailedauthorWigenborg, Gustav , The Swedish Energy Markets Inspectorate , Sweden
dc.contributor.detailedauthorHuang, Yalin, The Swedish Energy Markets Inspectorate , Sweden
dc.contributor.detailedauthorStröm, Lars , The Swedish Energy Markets Inspectorate , Sweden
dc.contributor.detailedauthorJohansson, Tommy , The Swedish Energy Markets Inspectorate , Sweden
dc.date.accessioned2019-07-24T12:38:08Z
dc.date.available2019-07-24T12:38:08Z
dc.date.conferencedate3-6 June 2019
dc.date.issued2019-06-03
dc.description.abstractThe national regulatory authority (NRA) for energy in Sweden, the Swedish Energy Markets Inspectorate (Ei), determines a revenue cap for each distribution system operator (DSO) and for the transmission system operator (TSO) for a regulatory period of four years at a time. The revenue cap is adjusted based on e.g. the performance regarding efficient grid utilization and continuity of supply. Ei aims to continuously evaluate and improve the regulatory framework for DSOs and the TSO.​This paper describes the efficient grid utilization incentive scheme with extra focus on upcoming changes from next regulatory period 2020-2023. This incentive scheme is divided into two parts: 1) reducing network losses and 2) reducing load flow peaks in connections to other grids (load). The most significant change about the first part (losses) is the introduction of a benchmarking method when calculating norm values taking the DSO’s individual objective conditions into consideration. The second part (load) has got a completely new structure, from comparing costs (that indirect partly depends on the load) to more directly comparing real achievements of the load. The indicator (average load factor) used to measure the load will remain the same but will evaluated further within the long-term development work at Ei.
dc.description.conferencelocationMadrid, Spain
dc.description.conferencenameCIRED 2019
dc.description.openaccessYes
dc.description.peerreviewedYes
dc.description.sessionDSO business environment enabling digitalization and energy transition
dc.description.sessionidSession 6
dc.identifier.isbn978-2-9602415-0-1
dc.identifier.issn2032-9644
dc.identifier.urihttps://cired-repository.org/handle/20.500.12455/213
dc.identifier.urihttp://dx.doi.org/10.34890/419
dc.language.isoen
dc.publisherAIM
dc.relation.ispartProc. of the 25th International Conference on Electricity Distribution (CIRED 2019)
dc.relation.ispartofseriesCIRED Conference Proceedings
dc.titleIncentive scheme for efficient grid utilization in the Swedish revenue cap regulation from 2020
dc.title.number948
dc.typeConference Proceedings
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
CIRED 2019 - 948.pdf
Size:
523.95 KB
Format:
Adobe Portable Document Format