Utilisation of Energy Storage to Improve Distributed Generation Connections and Network Operation on Shetland Islands
Loading...
Paper number
1764
Working Group Number
Conference name
CIRED 2019
Conference date
3-6 June 2019
Conference location
Madrid, Spain
Peer-reviewed
Yes
Short title
Convener
Authors
Fan, Fulin, University of Strathclyde, United Kingdom
Xu, Han, University of Strathclyde, United Kingdom
Kockar, Ivana, University of Strathclyde, United Kingdom
Xu, Han, University of Strathclyde, United Kingdom
Kockar, Ivana, University of Strathclyde, United Kingdom
Abstract
The Northern Isles New Energy Solutions (NINES) project
on the Shetland Islands seeks to trial the application of alternative
solutions, including demand side management and battery energy storage to
increase the integration of renewable generation and smooth the demand curve.
As part of the NINES project, a 1MW, 3MWh Battery Energy Storage System (BESS)
has been installed in the Shetland network and initially operated by an Active
Network Management (ANM) system and then brought under the manual scheduling.
The main objective was to reduce peak demands to be met by conventional
generation and also to increase the demand at off-peak times which may provide
additional headroom for non-firm distributed generation, i.e. ANM Controlled
Generation (ACG). This paper aims to present experiences and findings from the
NINES project regarding the BESS’s operation, utilisation and efficiency
(energy losses). Furthermore, the constraint rules that limit the ACG export
are discussed alongside practical issues around charging the BESS in response
to the ACG curtailment.
Table of content
Keywords
Publisher
AIM
Date
2019-06-03
Published in
Permanent link to this record
https://cired-repository.org/handle/20.500.12455/562
http://dx.doi.org/10.34890/786
http://dx.doi.org/10.34890/786
ISSN
2032-9644
ISBN
978-2-9602415-0-1