Operation of extensive grid automation: Challenges on the example of voltage control

Loading...
Thumbnail Image

Paper number

47

Working Group Number

Conference name

CIRED 2019

Conference date

3-6 June 2019

Conference location

Madrid, Spain

Peer-reviewed

Yes

Short title

Convener

Authors

Süfke, Christina, Westnetz GmbH, Germany
Schlenker, Nele, innogy SE, Germany
Heilemann, Ralf, Westnetz GmbH, Germany

Abstract

Ongoing grid integration of flexible and decentralized generation and load produces various challenges, such as problems concerning the allowed voltage bandwidth. Grid automation functions are developed to handle these challenges using intelligent methods. These functions can be realized centrally, locally or distributed. To operate the resulting multitude of different solutions, it is necessary to document these including the corresponding requirements and dependencies. Using the example of the wide area voltage control (WAVC), existing description options are explained and their deficits are named. In order to avoid additional expenses due to a lack of documentation, a uniform format and procedure for documentation is proposed.

Table of content

Keywords

Publisher

AIM

Date

2019-06-03

Permanent link to this record

https://cired-repository.org/handle/20.500.12455/60
http://dx.doi.org/10.34890/125

ISSN

2032-9644

ISBN

978-2-9602415-0-1