Impact of Voltage and Network Losses on Conductor Sizing and Topology of MV Networks with High Penetration of Renewable Energy Resources
Loading...
Paper number
949
Working Group Number
Conference name
CIRED 2019
Conference date
3-6 June 2019
Conference location
Madrid, Spain
Peer-reviewed
Yes
Short title
Convener
Authors
Millar, John, Aalto University, Finland
Saarijärvi, Eero, Trimble Solutions, Finland
Müller, Udo, Mitteldeutsche Netzgesellschaft Strom mbH, Germany
Fettke, Stephan, LEW Verteilnetz GmbH, Germany
Filler, Marko, Mitteldeutsche Netzgesellschaft Strom mbH, Germany
Saarijärvi, Eero, Trimble Solutions, Finland
Müller, Udo, Mitteldeutsche Netzgesellschaft Strom mbH, Germany
Fettke, Stephan, LEW Verteilnetz GmbH, Germany
Filler, Marko, Mitteldeutsche Netzgesellschaft Strom mbH, Germany
Abstract
This paper discusses heuristic distribution company planning rules, which are pragmatic but challenging to implement in a planning algorithm that aims to efficiently produce close to optimum solutions. The main focus is on how voltage is handled, and how other parameters, such as the cost of network losses and the time horizon used for planning, affect voltage. This is illustrated via Greenfield horizon plans and cost breakdowns based on a typical distribution network in the south of Germany.
Table of content
Keywords
Publisher
AIM
Date
2019-06-03
Published in
Permanent link to this record
https://cired-repository.org/handle/20.500.12455/214
http://dx.doi.org/10.34890/415
http://dx.doi.org/10.34890/415
ISSN
2032-9644
ISBN
978-2-9602415-0-1